Month End

Month End

Overview

In Workbench, at the end of each month/period, numerous documents generated and associated throughout the month, such as Purchase Orders, Plant issues, etc., need to be approved, batched, and exported to integrated financial system. Delays or omissions can lead to discrepancies and inaccuracies, not only within the Workbench but also between the Workbench and integrated accounting software like Xero, MYOB, and others.

Processing Methods

This process can be done either through:

The month end process should be run from module to module with the correct sequence:

  • Purchase Order

  • Timesheet

  • Plant

  • Stock

  • Accounts Payable Invoices.

  • Subcontract Claims

  • Accounts Receivable Invoices

  • Contract Claims

  • Adjustments

  • Inter-company

  • Forecast

  • Work in Progress

In general, for each module, actions may include:

  • Locking modules to prevent further input or modifications.

  • Completing requirements such as approvals, batching, and accruals.

  • Exporting data to financial software.

  • Closing module.

  • Forward to the next module until all are completed and exported.

 

Modules/documents may be batched and exported as needed throughout the month, depending on organisation’s accounting practices and financial software, not just only during the Month End process.

For manual process, this file can be used as the guideline.

Tools & Utilities

There are tools/screens and utilities that can be used during the month end process or as needed. Read more

 

Questions & Answers

The Month End Wizard doesn't need any new license. To set it up, users need to have System Administrator privileges and a Finance License for the Month End Person.

It is possible if User B also has the designated role specified in the setting screen. In such a scenario, User B can seamlessly resume the Wizard process without having to restart from the beginning.

There is only one Wizard instance (or process) at a time. The current instance must be finished before launching another.

Once the Wizard has been launched, cannot change the reporting period.

If MEW is in the 'Full' mode, you cannot open any completed module using the Wizard

There are 3 modules can be skipped: Timesheet, Plant and Stock, but they must be completed before processing the module Adjustment.