Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Overview:

IN PROGRESS...

Overview:

Resource Forecasting is optional in the monthly Contract Forecasting. This feature assists forecasting out the details of Labour and Equipment requirements to deliver the job.

This extension to forecasting allows you to plan out your Labour "Manning" and equipment requirement and project it out over the construction programme. This can be done for both internal and external resources.

The outputs of this feature are visibility of manpower or equipment required per week for a project and the expected costs. This will then feed into the Forecast and be incorporated into the Forecast Final cost calculation.

Quick Setup Guide:

A quick guide to enable Resource forecasting attached below:

View file
nameResource based Forecasting - setup guide.pptx

Screen Guide:

Image RemovedImage Added

Steps to create Labour Forecast and Plant Forecast:

Once the Forecast has been created for the selected period the Labour Forecast and Plant Forecast buttons take you to their respective forecasting screens. By clicking on these buttons and then saving, your Plant Forecast and Labour Forecast will be created.

The combined Costs from Labour and Plant Forecasts will feed into the main Forecast and be reflected in the column Resource Forecast. Drilling into the Labour or Plant Forecast from the main forecast using the hyperlinks in blue under the Resource Forecast column, allows you to only see that section of the job in the Resource Forecast screen. Notice the filters used at the top right of the screen.

Once the Forecast has been approved, the Labour and Plant Forecast buttons are disabled, and can only navigate to them through the hyperlinks.

External and Internal resources can be included in both Resource Forecasts.

Screen Guide for Labour and Plant Forecact screens:

Forecast displays 12 weeks by default. And the blue arrows at the top next to ‘Display From’, allow for navigating forwards or backwards to the future weeks. The Future column will display the number of weeks that have been used in this forecast. You can forecast several month in the future if required. All forecasted weeks (even when not visible on the current screen) will be reflected in the Labour/Plant Qty and Labour/Plant Totals columns respectively.

After saving the Labour Forecast or Plant Forecast, and going back to the main Forecast screen, the Resource Forecast value will be updated and will reduce/increase the Balance of Budget.

Columns:

  • Forecast From displays the year/period this forecast has been created for.

  • Display From is used to navigate through the future weeks of the project.

  • The blue arrows allow you to see further weeks in the screen. And importantly, the Future column shows if any values has been entered in future weeks that are not visible in the current displayed period.

  • Job, Work Centre, Activity are the same defined in the budget for this job. Only sections of the project that have 'By Cost Category' balance of budget type are shown.

  • Labour:

    • Employee Class will be available only for Time activities, and can be used for internal resources.

    • Rate will be derived from the Employee Class if selected, otherwise it can be manually entered.

  • Plant:


Image Removed
    • Plant Group allows you to narrow down the selection of the Plant Item

    • Plant Item can be selected to forecast the use of a specific Plant Item, which will enable the list of Rate Codes for this particular Plant Item and derive its Rate.

  • Qty/Wk defines the resource unit you will be using to forecast in the future weeks. See table Resource Definition Examples and Tips for Labour Forecasting below for clarification.

  • Comments use this field to clarify what has been defined in the Qty/Wk column. When an employee Class has been selected, you can specify your employee’s name here.

  • Budget Qty is populated with the quantity from the corresponding Budget line.

  • Budget is populated with the budget $ to spend on the project defined in the budget (down to Activity Code or employee class if used).

  • Actual Totals is the cost value for those actual hours that have been spent in the project so far up to the Forecast Period.

  • Labour Qty/Plant Qty are the quantity of hours that have been forecasted.

  • Labour Totals/Plant Totals are the total $ amounts for hours that have been forecasted.

  • Variance Qty is the calculation of Budget Qty - Actual Qty - Labour/Plant Qty

  • Variance is the calculation of Budget - Actual $ - Labour/Plant Totals

  • Week columns Are the weeks in the future where you will be forecasting your resources.

  • Internal displays a running total of quantities on the first line and value on the second line. Note that lines with Employee class / Plant Rate will fall into this running total.

  • External displays a running total of quantities on the first line and value on the second line. Note that lines with no Employee class or no Plant Rate will fall into this section, regardless of the activity type.

                                                                 

Forecast Labour:

Image Added

Works in conjunction with a monthly forecast and within the Month/Period snapshot. Labour Forecast allows you to forecast at weekly intervals. Why weekly? because when trying to manage man hours or people resources, the standard is a weekly calculation.                                                 

When expanding the Job in the screen, only sections of the project that have 'By Cost Category' balance of budget type, are shown. Each line can be expanded or drill down to Activity level, or Employee Class level in those cases where internal labour is being used. When External Labour is being used, no Employee Class will be selected. The Work Centres and Activities are the ones corresponding to those used in the Budget.

Use the New Line link to add a new line. When adding new line in the Labour Forecast:
When the activity is a Time type of activity, it will be used for internal employees, who are linked to an Employee Class. In this cases an Employee Class can be selected and the Rate will default from that Employee Class. You can then populate
When the activity is a Purchase type of activity, the Rate has to be manually entered. Lines with activity type Time and no employee class, or lines with activity type Purchase, these lines are considered external resources.
Populate how many hours per week this resource will be needed, and add some comments to explain what that resource is: whether is Hours per week for 1 operator, or 4 operators for example. Note that the Hrs/Wk quantity can be dfined defined per resource or for the sum of resources by employee class; so it is important to add comments. The calculation for the Labour Cost column is: Rate * Hrs/Wk * Sum of Weeks

ExampleResource Definition Examples:

 

Employee Class

Rate

Hrs/Wk

Comments

Week 1

Week 2

Labour Total

Option 1

Site Manager

60

40

Fred Smith the foreman.

1

1

4800

Option 1

Site Manager

60

40

Roger Smith Lawson the foreman.

1

1

4800

Option 2

Site Manager

60

40

Fred Smith and Roger Lawson.

2

2

9600

Option 3

Site Manager

60

80

Fred Smith and Roger Lawson.

1

1

9600

 

Columns:

Budget Qty is populates with the quantity from the Budget line

Budget is populated with the budget $ to spend on the project defined in the budget (down to Activity Code or employee class if used).

 

Forecast displays 12 weeks by default. And the blue arrows at the top next to ‘Display From’, allow for navigating forward or backward to the future or past weeks if they exist. The Future column will display the number of weeks that have been used in this forecast. You can forecast several month in the future if required. All forecasted weeks (even when not visible on the current screen) will be reflected in the Labour Qty and Labour Totals columns.

After saving the Labour Forecast, and going back to the main Forecastscreen, the Resource Forecast value will be updated and will reduce/increase the Balance of Budget.

 

 

 

Forecast Plant:

Info

LABOUR FORECAST TIPS

  • Forecast Internal Resources using Employee Classes and Time Activities

  • Forecast External Resources against Purchase Activities and define your rates and work hours.

  • When choosing internal people resources you can add a row per person and add the intended persons name in the comments (A bit like a resource schedule).

  • If you are forecasting a team of people e.g. we need 5 tradesman for this section of work, you can enter it as one row just remember in the week columns the Qty will then refer to the number of people per week.

  • Where you are using the same resource in multiple places in a project you can actually enter a part quantity e.g. you could enter .5 of a man in against 2 different areas of a job to indicate that in the week he would be splitting his time between those 2 areas.

Forecast Plant:

Image Added

It is very similar to Labour Forecast, with the difference that you can select specific plant items.

Internal and external equipment can be used. On Internal plant, a rate can be selected, when there are multiple rates in that Plant item. For external Plant items, a manual rate is to be entered.

 

Screen Guide for Labour and Plant Forecact screens:

  • Forecast From displays the year/period this forecast has been created for.

  • Display From is used to navigate through the future weeks of the project.

  • The blue arrows allow you to see further weeks in the screen. And importantly, the Future column shows if any values has been entered in future weeks that are not visible in the current displayed period.

                                                                 

Next Steps:

Plant Group selection will narrow your Plant Items selection. Plant Rate Codes will be displayed for the specific Plant Item selected. And this Plant Rate Code will populate the Rate. When a Plant item is selected, this will be included in the Internal totals at the bottom. To forecast external plant, a manual rate can be entered, and the totals will become part of the External totals at the bottom.

Info

PLANT FORECAST TIPS

  • Forecast Internal Resources using Plant Groups, Items and Rates

  • Forecast External Resources against Purchase Activities and define your rates and work hours.

Next Steps:

Sharperlight has all the Resource Forecast information to be able to create a custom report displaying the specific information you need.

FAQs:

Filter by label (Content by label)
showLabelsfalse
showSpacefalse
cqllabel = "forecast" and space = "KB"

Process Flow: