3.2.2.56
29 August 2016
Â
Â
Daily Diary:
External Plant:
- 3 new columns added to the External plant screen:
-Job Code
-Rate, which comes from Docket Costing Schedule rate and can be changed if needed.
-Cost, to reflect total value of Rate * Qty entered. Read only. - Work centre selection shows correct Job Work centre description if there is one available, otherwise it shows Work Centre description.
Â
Internal Plant:
- Work centre selection shows correct Job Work centre description if there is one available, otherwise it shows Work Centre description.
- Activity list is limited to activity type = Plant. Purchase activities are no longer available.
Â
Materials:
- Work centre selection shows correct Job Work centre description if there is one available, otherwise it shows Work Centre description.