title3. ITP Module Heirachy

Below is a diagram that explains the relationship between the ITP Template, Tasks, Activities and ITC’s

Drawio
mVer2
simple0
zoom1
simple0
inComment0custContentId3088220204
pageId3086581762
lboxcustContentId13088220204
diagramDisplayNameUntitled Diagram-1718146961265.drawio
lbox1
contentVer34
revision34
baseUrlhttps://webwbdoc.atlassian.net/wiki
diagramNameUntitled Diagram-1718146961265.drawio
pCenter0
width840.4999999999995
links
tbstyle
height752

...

  1. Once created, you will see the ITC’s as a draft linked to the project
    View the draft ITCs linked to the project, with % completion visible in the pop-up window and on the form.

image-20240612-011832.png

3. Re-Ordering ITP Activities

In some scenarios, you may need to re-order activities in an ITP (Inspection Test Plan) to accommodate additional activities or update the sequencing in the ITP Booklet. To do this, follow these steps:

Steps

Screen guide

  1. Click on the "Re-Order Activities" Button: Start by clicking the button labeled "Re-Order Activities."

image-20240806-235703.pngImage Added

  1. Select and Drag Activities: Once the list of activities appears, you can select and drag them to the desired position in the sequence.

Click-drag ITP act.gifImage Added

  1. Save Changes: After arranging the activities in the correct order, save the changes to update the ITP Booklet. Click the “back arrow” to save and return to the ITP form

image-20240806-235926.pngImage Added

These steps will ensure that your ITP Booklet reflects the correct sequence of activities, maintaining clarity and accuracy.

image-20240807-000107.pngImage Added