Overview:

Just like productive Jobs can have a Job BudgetPlant Items can have a Plant Budget. These budgets are most commonly used when performing work, upgrading, or modifying a plant item. You can budget for the anticipated labour and part costs and measure your actual expenditure against what you budgeted for. Revenue is not included in plant budgets.

This screen is reached by navigating to Plant Items, then clicking on the blue ellipsis button on the item you want to budget for and selecting Plant Budget.

Screen Guide:

Initial List

Image Removed
Image Added
  • + New Plant Budget

 will are
  •  will open the new budget screen.

  • Filters

 
  •  are available to narrow down the budgets you wish to see.

  • Budget Header

 is
  •  is the Hierarchy Level 1 Job, or the top-level Plant Item if there are subjobs present. Budget containers can have lines for multiple Plant Items in the hierarchy.

  • Internal Reference

 is
  •  is a required free text field that keeps your budgets organised, and serves as a link to

the 
  • the Create/Edit Budget screen. This can be whatever your company needs it to be to match internal expectations.

  • Description

 is
  •  is custom text meant to define what the budget container represents.

  • Year/Period

 is
  •  is the financial year and period in which this budget was created. Note that this field will affect which periods this budget is recognised in reports.

  • Budget Date is the date that was entered as the creation date for this budget. This date determines

what 
  • what Year/Period

 it
  •  it is in.

  • Cost Rate is the total of all cost rates in the underlying budget lines.

  • Cost

 is
  •  is the total cost amount of all underlying lines that this budget contains.

  • Approved Date is the date that this budget was approved if your company uses budget approval.

Create/Edit Budget

Image Removed

image-20240520-223713.pngImage Added

Header:

  • Plant Code

 is
  •  is automatically populated from the selected Plant Item.

  • Budget Type

 can
  •  can be one of the following:

    • Original Contract - the original work planned.

    • Approved Variations - for all variations to the original work.

    • Increased Costs - a budget type that can be used to add expected costs.

    • Other Costs - a generic type that your company can use in whatever manner it deems appropriate.

  • Budget Date determines

which 
  • which Year/Period

 this
  •  this budget begins in. Note that budgets which exist in a period beyond that of a report or forecast's parameters will not be included in said report.

  • Year/

Period 
  • Period is derived from the Budget Date

 field
  •  field.

  • Internal Reference is a required field, and the primary link from the previous screen. The reference must be unique within the Plant Item.

  • Description is custom text meant to define what the budget container represents. This is important for variations to make sure your team knows what the variation signifies. This field is limited to 50 characters.

  • Details is an optional field to give more definition or explanation to the budget. This field is limited to 2000 characters.

Lines:

  • Type begins the process of determining which cost element is being used for this line. You can select from the following types, after which the field selections on the line will change:

    • Activity allows you to enter a traditional Activity directly on the line, and will disable the Line Code

 and 
    •  and Plant Rate

 fields
    •  fields.

    • Employee provides a selection of Users, populating the cost fields with the selected user's Employee Class rate.

    • Labour

 changes
    •  changes the Line Code

 picker
valid 
    • valid Activity, Work Centre,

and 
    • and Quantity, but

the 
    • the Cost

 fields
    •  fields will automatically be populated with the chosen Employee Class data.

    • Plant changes the Line Code picker to select from Plant

 items
    •  itemsPlant Rate

 will
    •  will be populated with the default rate set up in the plant item, but can be changed if needed. The Activity

 will
    •  will also be set to the default activity for the selected plant item, but you will need to select the Work CentreDescription, Unit, and Cost Rate will also default from the plant item, leaving Quantity

 to
    •  to be entered.

    • Item changes the Line Code

 picker
    •  picker to select from Stock

 items
    •  itemsPlant Rate

 will
    •  will be unavailable

and 
    • and Activity, Description, Unit, and Cost Rate

 will
    •  will be derived from the item defaults, leaving Work Centre

 and 
    •  and Quantity

 to
    •  to be entered.

  • Line Code

 will
  •  will change depending on the element Type being used.

  • Plant Rate

 will
  •  will display all available rates for the selected plant item in Line Code

 when
  •  when the Plant Type is selected.

  • Activity

 may
  •  may default depending on the Type

 used
  •  used, but this can be manually changed. Availability depends on the Activities

 in
the 
for the 
  • for the Plant Item.

  • Description will default based on the previous selection, but can be modified.

  • Unit is the unit of measurement for this line.

  • Qty is the quantity of units being budgeted.

  • Cost Rate may default based on the previous selection but can be modified.

  • Cost is the Qty

 multiplied
  •  multiplied by the Cost Rate

 fields
  •  fields.

  • Details is an option field to add more information or specification about the line.

The 
  • The Bin column allows you to select lines to delete. Be sure to tick each checkbox that you wish to delete then click Save.

Button Section:

  • Print will generate the default budget report . Other reports may be available as well using the ^ button.

  • Attachments

 can
  •  can be added using this button. Some examples would be a budget workup spreadsheet, quotes from suppliers, etc.

  • Import is available to bring in data from a spreadsheet, and has multiple import methods using the ^ button. Note that the data must match the expected column format and requirements exactly for the import to be successful.

  • New Line adds a blank line to the above section.

  • New Plant Budget is useful when you need to enter multiple budgets after each other. This button creates a new blank budget for the same Plant Item.

  • Delete

 will
  •  will attempt to delete the entire budget (not individual lines). This button will be pale red if there are budget lines present. You must delete all lines before deleting the budget container itself.

  • Save

 will
  •  will attempt to commit all entered data to the system. If there are any errors, a red bar will display at the top of the screen with the error. You must fix these errors before the data will be committed to the system. A green bar will appear if the data has been saved.

Next Steps:

Once budgets are entered, they can be viewed and tracked in Plant Enquiry.