  • Budget must be created first.

  • Budget’s Input must be At Revenue & Cost Element (not At Cost Element, nor At Activity, Work Centre), which has a format of Revenue lines and cost lines under each Revenue line. The Revenue lines are Benchmark Project Items, and the Cost lines are the Benchmark Resources.

  • Import stored procedure is Benchmark Budget Import (wbImportBenchmarkBudget).

  • Import does not allow any lines that have a Line Cost = 0. This must be removed from the file first.

Image Added

Tips to troubleshoot errors:

...